  Tower Talk: The Narrows Crossing Project

Construction Information

Our design-build contractor, Shaw Energy Delivery Services, has made significant progress on the Narrows Crossing project. The crews have worked simultaneously on the both sides of the water. Here's a recap of what's happened so far.

March 2007
Final testing and site demobilization.

February 2007
Removal of old foundations and final grading.

December 2006 & January 2007
Removal of old towers was finalized.

November 2006
Removed old wires.

October 2006
New wire installation was completed.

August & September
Henkels and McCoy, a subcontractor installed the new wires on the towers. The team ran into some bumps along the way--the biggest one was when a "sock line" broke as it pulled a wire across the waterway. No one was hurt, but fixing the problem took some time.

July
Local residents watched as the construction team simultaneously built the two, 450-foot towers on each side of the waterway. Most of the visible construction on the new towers took place at the end of June and July.

June
 Crews poured the foundations for the supporting towers.

May
Steel for the main towers arrived on site and crews began putting pieces of the new towers together.

April
The four foundations for each tower were poured. The main tower foundations are 6 feet in diameter and 60-feet deep.

March
The construction team prepared the site by grading, clearing and trimming trees.

Photo Gallery

Top of Page                                             

 

   

 

 

Home | Site Map | About Us | Contact Us | Search | Links

Click! Network | Tacoma Public Utilities | Jobs

Send questions or comments about the Tacoma Power Web site to power@cityoftacoma.org

Copyright © 2002 Tacoma Power. All rights reserved. Designed and maintained by Lelian Solip . A service of the City of Tacoma.