Interconnection
of Electric Generators
Generating
Capacity Of Not More Than 25 kiloWatts
Table of Contents
Chapter 1 Purpose and Scope
Chapter 2 Application of Rules
Chapter 3 Definitions
Chapter 4 Technical
Standards for Interconnection
Chapter 5 Application for
Interconnection
Chapter 6 General Terms and
Conditions of Interconnection
Chapter 7 Certificate of
Completion
Chapter 8 Required Filings –
Exceptions
1. The purpose of this chapter is to establish
rules for determining the terms and conditions governing the interconnection of
electric generating facilities with a nameplate generating capacity of not more
than 25 kilowatts to the electric system of Tacoma Power.
2. These rules are intended to be consistent
with the requirements of chapter 80.60 RCW, Net Metering of Electricity; to
partially comply with Section 1254 of the Energy Policy Act of 2005, Pub. L.
No. 109-58 (2005); and to promote the purposes of Substitute Senate Bill 5101,
Chapter 300, Laws of 2005 (effective
Chapter 2 Application of rules
1. These rules include various requirements
applicable to Tacoma Power, the applicant and the generator.
2. These rules modify, if necessary, any
existing interconnection rules of Tacoma Power, including but not limited to,
rules implementing chapter 80.60 RCW, Net Metering of Electricity.
Chapter 3 Definitions
“Applicant”
means any person, corporation, partnership, government agency, or other entity
applying to interconnect a generating facility to Tacoma Power’s electric
system pursuant to this chapter.
“Application”
means the written notice as defined in WAC 480-108-030 provided by the
applicant to Tacoma Power that initiates the interconnection process.
“Certificate of completion”
means the attached certificate furnished by Tacoma Power and completed by the
applicant or generator and the electrical inspector having jurisdiction over
the installation of the facilities indicating completion of installation and
inspection of the interconnection.
“Electric
system” means all electrical wires, equipment, and other facilities owned or
provided by Tacoma Power that are used to transmit electricity to customers.
“Generating
facility” means a source of electricity owned by the applicant or generator
that is located on the applicant’s side of the point of common coupling, and
all facilities ancillary and appurtenant thereto, including interconnection
facilities, which the applicant requests to interconnect to Tacoma Power’s
electric system.
“Generator”
means the entity that owns and/or
operates the generating facility interconnected to Tacoma Power’s electric
system.
“Initial
operation” means the first time the generating facility is in parallel
operation with the electric system.
“In-service date” means the date on which the
generating facility and any related facilities are complete and ready for
service, even if the generating facility is not placed in service on or by that
date.
“Interconnection” means the physical connection of a
generating facility to the electric system so that parallel operation may
occur.
“Interconnection agreement”
means the standardized terms and conditions that govern the interconnection of
generating facilities pursuant to these rules.
The model interconnection agreement may be modified to accommodate terms
and conditions specific to individual interconnections, subject to the
conditions set forth in these rules.
“Interconnection facilities” means the electrical
wires, switches and other equipment used to interconnect a generating facility
to the electric system.
“Net
metering” means measuring the difference between the electricity supplied by
Tacoma Power and the electricity generated by a generating facility that is fed
back to Tacoma Power over the applicable billing period.
“Network
distribution system (grid or spot)” means electrical service from a
distribution system consisting of two or more primary circuits from one or more
substations or transmission supply points arranged such that they collectively
feed secondary circuits serving one (a spot network) or more (a grid network)
Utility customers.
“Parallel
operation” or “operate in parallel” means the synchronous operation of a
generating facility while interconnected with Tacoma Power’s electric system.
“Point of common coupling” or “PCC” means the point where the
generating facility’s local electric power system connects to Tacoma Power’s
electric system, such as the electric power revenue meter or at the location of the
equipment designated to interrupt, separate or disconnect the connection
between the generating facility and Tacoma Power.
“Utility” means Tacoma Power who owns and operates the electrical
distribution system, or the electrical distribution system itself, onto which
the applicant seeks to interconnect a generating facility.
Chapter 4 Technical Standards for Interconnection
The technical standards listed in this section shall apply to all
generating facilities to be interconnected to Tacoma Power under this chapter.
a. Any generating
facility desiring to interconnect with Tacoma
Power’s electric system or modify an existing
interconnection must meet all minimum technical specifications applicable, in
their most current approved version, as set forth in this chapter.
b. The specifications and requirements
in this section are intended to mitigate possible adverse impacts caused by the
generating facility on Utility equipment and personnel and on
other customers of Tacoma Power. They
are not intended to address protection of the generating facility itself,
generating facility personnel, or its internal load. It is the responsibility of the generating
facility to comply with the requirements of all appropriate standards, codes,
statutes and authorities to protect its own facilities, personnel, and loads.
c. The specifications and
requirements in this section shall apply generally to the non- Utility-owned
electric generation equipment to which this standard and agreement(s) apply
throughout the period encompassing the generator’s installation, testing and
commissioning, operation, maintenance, decommissioning and removal of said
equipment. Tacoma Power may verify
compliance at any time, with reasonable notice.
d. The generator shall comply with the requirements in subsections
(d)(i), (d)(ii) and (d)(iii). However, at its sole discretion, Tacoma Power
may approve alternatives that satisfy the intent of, and/or may excuse
compliance with, any specific elements of these requirements.
i. Code and standards. Applicant shall conform to all applicable
codes and standards for safe and
reliable operation. Among these are the
National Electric Code (NEC), National Electric Safety Code (NESC), the
ii. Safety. All safety and operating procedures for
joint use equipment shall be in compliance with the Occupational Safety and
Health Administration (OSHA) Standard 29, CFR 1910.269, the NEC, Washington
Administrative Code (WAC) rules, the Washington Industrial Safety and Health
Administration (WISHA) Standard, and equipment manufacturer’s safety and
operating manuals.
iii. Power Quality. Installations will be in compliance with all
applicable standards including IEEE Standard 519-1992 Harmonic Limits.
a. Applicant shall furnish and install on applicant’s side of the meter, a UL-approved safety disconnect switch which
shall be capable of fully disconnecting the applicant's generating facility
from Tacoma Power’s electric system. The
disconnect switch shall be located adjacent to Utility
meters and shall be of the visible break type in a metal enclosure which can be
secured by a padlock. The disconnect
switch shall be accessible to Tacoma Power
personnel at all times.
b. The
requirement in subsection (2)(a) above may be waived by Tacoma Power if: (i) applicant provides interconnection
equipment that applicant can demonstrate, to the satisfaction of Tacoma Power,
performs physical disconnection of the generating equipment supply internally;
and (ii) applicant agrees that its
service may be disconnected entirely if generating equipment must be physically
disconnected for any reason.
c. Tacoma
Power shall have the right to disconnect the generating facility at the
disconnect switch under the following circumstances: when necessary to maintain safe electrical
operating conditions; if the generating facility does not meet required
standards, or these rules; if the generating facility at any time adversely
affects or endangers any person, the property of any person, Tacoma Power’s
operation of its electric system or the quality of Tacoma Power’s service to
other customers; or failure of the owner of record, as filed with Tacoma Power,
to notify Tacoma Power of a sale or transfer of the generator, interconnecting
facilities or the premises on which the generator is located.
d. Nominal
voltage and phase configuration of applicant’s generating facility must be
compatible to Tacoma Power system at the point of common coupling.
a. IEEE Standard
1547-2003, Standard for Interconnecting Distributed Resources with Electric
Power Systems.
b. UL Standard 1741,
Inverters, Converters, and Controllers for Use in Independent Power Systems. Equipment must be UL listed.
c. IEEE Standard
929-2000, IEEE Recommended Practice for Utility Interface of Photovoltaic (PV)
Systems.
a. IEEE Standard
1547-2003, Standard for Interconnecting Distributed Resources with Electric Power Systems.
b. ANSI Standard C37.90, IEEE Standard for Relays and Relay Systems Associated
with Electric Power Apparatus.
c. Applicants
proposing such interconnection may also be required to submit a power factor
mitigation plan for Utility review and approval.
Chapter 5 Application for Interconnection
1. When an applicant requests interconnection from Tacoma
Power, the applicant shall be responsible for conforming to the rules and
regulations that are in effect and on file with Tacoma Power. Tacoma Power will designate a point of
contact and provide a telephone number or website address for this purpose. The applicant
seeking to interconnect a generating facility under these rules must fill out
and submit a signed application form.
Information must be accurate, complete, and approved by Tacoma Power
prior to installing the generating facility.
2.
Fees. Tacoma
Power’s interconnection fee is the $50 required for an electrical permit. Additional charges may apply if additional
inspections are required for completion.
Renewable Energy Annual Incentive Payment Program. A $25 fee is required if customers wish to
participate and receive annual payments for renewable energy production. The fee must be submitted with your
application for the Renewable Energy System Annual Incentive.
Production meter fees. Tacoma Power
requires that the customer have a utility-owned meter installed. The charge for the installation of a
utility-owned production meter is $75.54.
3.
Application
Prioritization. All generation interconnection
requests pursuant to this chapter will be prioritized by Tacoma Power in the
same manner as any new load requests.
Preference will not be given to either request type. Tacoma Power will process the application and
provide interconnection in a time frame consistent with the average of other
service connections.
4. Application evaluation. All generation interconnection requests
pursuant to this chapter will be reviewed by Tacoma Power for compliance with
these rules. If Tacoma Power in its sole
discretion finds that the application does not comply with this chapter, Tacoma
Power may reject the application. If
Tacoma Power rejects the application it shall provide the applicant with
written notification stating its reasons for rejecting the application.
Chapter 6 General Terms and Conditions of Interconnection
The general terms and conditions listed in this section shall apply to
all generating facilities interconnecting to Tacoma Power.
1. Any electrical generating
facility with a maximum electrical generating capacity of 25 kW or less must
comply with these rules to be eligible to interconnect and operate in parallel
with Tacoma Power’s electric system. The rules under this chapter shall apply to all
interconnecting generating facilities that are intended to operate in parallel
with Tacoma Power’s electric system irrespective of whether the applicant
intends to generate energy to serve all or a part of the applicant’s load; or
to sell the output.
2.
In order to
ensure system safety and reliability of interconnected operations, all
interconnected generating facilities shall be constructed and operated by
generator in accordance with this chapter and all other applicable federal,
state, and local laws and regulations.
3.
Prior to initial
operation, all generators must submit a completed certificate of completion to
Tacoma Power; execute the appropriate interconnection agreement contained in
Attachment C, and any other agreement(s) required by these rules for the
disposition of the generating facility’s electric power output. The
interconnection agreement between Tacoma Power and generator outlines the
interconnection standards, cost allocation and billing agreements, and on-going
maintenance and operation requirements.
4.
Applicant or
generator shall promptly furnish Tacoma Power with copies of such plans,
specifications, records, and other information relating to the generating
facility or the ownership, operation, use, or maintenance of the generating
facility, as may be reasonably requested by Tacoma Power from time to time.
5. For the purposes of public
and working personnel safety, any non-approved generation interconnections
discovered will be immediately disconnected from Tacoma Power’s system.
6.
To ensure
reliable service to all Tacoma Power customers and to minimize possible
problems for other customers, Tacoma Power will review the need for a
dedicated-to-single-customer distribution transformer. Interconnecting generating facilities under 25 kW may require a separate transformer. If Tacoma Power requires a dedicated
distribution transformer, the applicant or generator shall pay for all costs of
the new transformer and related facilities.
7.
Metering.
a.
Net Metering for
Solar, Wind, Hydropower and Fuel Cells as set forth in RCW 80.60: Tacoma
Power shall install, own and maintain a kilowatt-hour meter, or meters as the
installation may determine, capable of registering the bi-directional flow of
electricity at the point of common coupling at a level of accuracy that meets
all applicable standards, regulations and statutes. The meter(s) may measure such parameters as
time of delivery, power factor, voltage and such other parameters as Tacoma
Power shall specify. The applicant shall
provide space for metering equipment. It
will be the applicant’s responsibility to provide the current transformer
enclosure (if required), meter socket(s) and junction box after the applicant
has submitted drawings and equipment specifications for Tacoma Power’s approval.
Tacoma Power may approve other generating sources for net metering but is not
required to do so.
b.
Production
Metering:
10. Prior to any future modification or expansion of the
generating facility, the generator will obtain Utility review and
approval. Tacoma Power reserves the right to require the generator, at the generator’s
expense, to provide corrections or additions to existing electrical devices in
the event of modification of government or industry regulations and standards.
Chapter 7 Certificate of completion
All generating facilities must obtain an electrical permit and pass electrical inspection before they can be connected or operated in parallel with Tacoma Power’s electric system. Generator shall provide written certification to Tacoma Power that the generating facility has been installed and inspected in compliance with the local building and/or electrical codes.
Chapter 8 Required filings – Exceptions
Tacoma Power shall maintain
on file for inspection at its place of business, the charges, terms and
conditions for interconnections pursuant to these rules. Such filing includes forms of the following
documents and contracts:
Tacoma Power may grant such
exceptions to these rules as may be appropriate in individual cases.