Electrical Service Requirements

New Electrical Service Hookups

Residential Project Development Process

1.   The customer completes the application

The customer completes the New Services Application and submits it to the New Services Engineering office along with the following documents:

  • Plat maps and engineering plans for all utilities
  • Road way designs
  • Plans on an AutoCad disc
  • Voltage and electrical load requirements
  • Joint trench participants

2.  Tacoma Power's New Services Engineering group prepares the following.  Response time is approximately two weeks.

  • Reviews plans and makes a site visit.
  • Prepares the design and Agreement, and calculates the project cost and engineering deposit.

3.   The deposit is paid by the customer.

4.  Engineering completes the following:

  • The detailed electrical design and plans.
  • The preliminary construction drawing is sent to the customer, public agencies, and other utilities.

5.  The customer provides full payment.

  • Payment must be paid in full before the construction drawing is completed and released for construction.
  • The customer must submit any revised plans prior to Engineering's release of the construction drawing.

Top of Page                                             

 

 

   

 

Home | Site Map | About Us | Contact Us | Search | Links

Click! Network | Tacoma Public Utilities | Jobs

Send questions or comments about the Tacoma Power Web site to power@cityoftacoma.org

Copyright © 2002 Tacoma Power. All rights reserved. Designed and maintained by Lelian Solip . A service of the City of Tacoma.